Apartment: 4 to 7 working days
Two to three rooms, including filling, sanding and two coats. Moving out furniture adds a day at each end.
House: 2 to 4 weeks
Interior walls, ceilings and trim across two floors, room by room so you can keep living there. Exterior work is quoted separately.
Commercial floor: 1 to 2 weeks
Office and retail spaces run in stages outside opening hours, which stretches the calendar but protects trading.
- Survey and colour decisions first
- Preparation is 40% of the schedule
- Weather moves exterior dates